Effort is a concept that allows entry of an initial estimate of the ease/difficulty of certain
Events as well as entry of the final assessed ease/difficulty of that particular job, using the
same scale for measurement. The idea is to be able to compare the ease/difficulty of the
Event as performed with that originally estimated and to enable consistency of comparison
of effort between different Events and across Clients. The choice of units of effort is down
to the user and is not specified or given a label within the system other than "Points" - an
abstract unit of effort could be used or, for example, units of time such as hours or
minutes.
You are able to produce two types of effort summaries report, as mentioned below. You
would have had to add effort details for the client’s events while adding a task/appointment
in the system.
Creating Effort Points
You will first need to create the effort points in the system. To do this follow the steps
below:
• Go to Administration > Data > Effort from the top toolbar
• Click on New Record on the toolbar
• Enter Description & Effort Points
• Click on Save
Client Effort Summary Report
The Client effort summary report produces a list of clients with effort data, for example
Estimated Fee. You are also able to drill down to view the effort details for each event for
the client. Please follow the instructions below on how to produce this report:
• From the top toolbar, go to Reports > Effort Summaries > Client Effort Summary
The report will have an overall list of clients, number of events, estimated effort &
remaining effort along with estimated fee for the effort taken.
• To view individual client’s effort data, select the client from the above list
• Click on View Client Effort Detail
The above report lists effort data for a particular client’s events in the system
Event Effort Summary report
The Event Effort Summary report produces a list of the type of events worked on in the
system along with effort data, for example Estimated Fee. You are also able to drill down
to be able to view the effort details for a particular type of event along with its client’s
details. Please follow the instructions below on how to produce this report:
• From the top toolbar, go to Reports > Effort Summaries > Event Effort Summary
The report will have an overall list of events, number of events, estimated effort &
remaining effort along with estimated fee for the effort taken.
To view a particular event type effort data, select the event from the above list and
Click on View Event Effort Detail or;
• Double right click on the event
The above report lists effort data for a particular event type along with the
associated client
• Double right clicking on an event will open the task
Activity Time Log Summaries
BTCSoftware automatically records time spent on a system defined task (e.g., Tax Return,
Year End Accounts, VAT Return, or any other HMRC Forms). Logging of time on the
activity of a task takes place only when the task is in edit mode. Activity on a task continues
to be logged even if there are no active key strokes/entries being made on the active task
as long as the task remains in edit mode.
Idle Time is calculated depending on the Idle Start Threshold set up on the software. To
check this:
• Go to Administration > System > Options from the top menu